Moving into a newly built home: check the Wkb completion notification first

When may you use your newly built home? Check the completion notification, the quality assurance provider’s declaration, the dossier documents and the waiting period.

Duration: 1:56Published on Part of: All explainer videos

Summary

When may you use your newly built home? Check the completion notification, the quality assurance provider’s declaration, the dossier documents and the waiting period.

Key points

  • You receive the keys to your newly built home. Can you move in straight away? First check which construction procedure applies to your home. Certain newly built homes covered by the Dutch Construction Quality Assurance Act (Wet kwaliteitsborging voor het bouwen, Wkb) require a completion notification.
  • This must include the quality assurance provider’s declaration and the required information about the building. A key handover or signed acceptance report does not replace that notification. So ask who will submit the dossier, which documents are still missing and when everything has been supplied to the municipality.
  • If the notification is incomplete, you cannot simply count from the initial submission date. The official guidance provides for a period of two weeks after a complete completion notification before use may begin.
  • Other rules also continue to apply. Are you taking delivery of the home as a shell? Discuss in advance which finishing work of your own still needs to be inspected. Missing ventilation data, for example, may prevent the declaration from being issued.

Please note

Not legally reviewed yet

Sources for this video
  1. iplo.nl
  2. iplo.nl
  3. iplo.nl
  4. iplo.nl
  5. rijksoverheid.nl
  6. tlokb.nl
  7. zoek.officielebekendmakingen.nl

Transcript

Construction law in the Netherlands.

You receive the keys to your newly built home. Can you move in straight away? First check which construction procedure applies to your home. Certain newly built homes covered by the Dutch Construction Quality Assurance Act (Wet kwaliteitsborging voor het bouwen, Wkb) require a completion notification.

This must include the quality assurance provider’s declaration and the required information about the building. A key handover or signed acceptance report does not replace that notification. So ask who will submit the dossier, which documents are still missing and when everything has been supplied to the municipality.

If the notification is incomplete, you cannot simply count from the initial submission date. The official guidance provides for a period of two weeks after a complete completion notification before use may begin.

Other rules also continue to apply. Are you taking delivery of the home as a shell? Discuss in advance which finishing work of your own still needs to be inspected. Missing ventilation data, for example, may prevent the declaration from being issued.

Coordinate your move with the dossier schedule. Keep the submitted documents, acknowledgement of receipt and any questions from the municipality. If a dispute arises about occupation or additional costs, have your specific dossier assessed.

This explanation concerns Dutch law, checked on 25 October 2026. As at that date, this public-law quality assurance procedure does not yet apply to ordinary alterations to existing buildings.

Read the full article and sources. General information does not replace advice about your own situation.

Download the transcript

Timestamps

Select a timestamp to jump to that part of the video.

Related topics

Your next step

Help with your legal question.

Briefly describe your situation and the help you need.

Open the help form
Construction law
Your next step

Help with your legal question.

Briefly describe your situation and the help you need.

Find a lawyer
Open the help form
PrivacyGeneral information

Find a topic

Search by question or topic.

Popular topics

Contractor will not repair defects after completion: what can you do?Disputing a contractor’s extra-work bill: when is legal help useful?Contractor stops without finishing your renovation: what can you do?Putting a contractor in default: a notice suited to your building problemFixed price, guide price or time and materials: what building risk are you accepting?Having a building quotation checked: what does your assignment really include?Contractor wants a large advance: what should you check and when seek legal help?Building guarantee rejected or contractor bankrupt: when you need a construction lawyerBuilding expert in a contractor dispute: what investigation helps your lawyer?Withholding payment to a contractor: what sum can you reasonably retain?Terminating a building contract for breach: organise grounds, evidence and settlementRenovation overruns: when can a lawyer help with building delay?Damage during your renovation: preserve evidence and seek legal helpHidden building defect discovered: investigate without losing evidenceYour contractor is bankrupt: steps before transferring the building workObjecting to a building permit: deadlines, urgency and environmental-law adviceBuilding stop imposed: decision, penalty and urgent legal adviceBuilding dispute: court, arbitration or a complaints committee?What repair deadline should you give a contractor? Make it feasible and verifiableNeed a construction lawyer? Choose help suited to your building disputeHave your building contract reviewed before accepting construction risksRenovation terms and conditions: have disputed building clauses assessedAgreeing reduced work: avoid disputes about omitted work and the final priceThe contractor’s duty to warn: was the risk clearly reported in time?Preparing for handover: check the work, reservations and documentsThe five-percent arrangement for new homes: monitor the deposit, deadline and defectsChecking a building omgevingsvergunning: activities, drawings and starting workBuilding without a permit: check both building aspects before startingConstruction damage from work next door: evidence and legal adviceBuilding near a property boundary: ownership, permits and agreements with neighboursArchitect liable for a construction defect: what work was agreed?Structural engineer liable for a calculation error or structural problem?Construction insurer refuses cover: what does your CAR policy say?Contractor retains control of the site: when does a right of retention apply?Dispute with a subcontractor: whom do you approach and who pays?Dispute under UAV or UAV-GC: check your contract version firstConstruction arbitration at the RvA: preparing jurisdiction, evidence and costsRecovering construction delay losses: which costs can you substantiate?Penalty clause in a construction contract: when can you claim a penalty?Contractor requests a price increase after signing: must you pay extra?Disputing a construction invoice: check the items and support your objectionDisputing a handover report: correct the record and preserve evidenceHaving another contractor repair a construction defect: prepare the transitionDispute with a property developer: who must honour your agreement?Construction damage from municipal works: approach the municipality or contractor?Enforcement request concerning building work: seek investigation and a decisionConstruction defects: distinguish complaints, limitation and interruptionConstruction defects and the owners’ association: who may claim against the contractor?Holding a contractor liable for damage: cause and evidenceConstruction settlement agreement: define repairs and releasesMoving into a newly built home: check the Wkb completion notification firstContractor will not repair defects after completion: what can you do?Contractor stops without finishing your renovation: what can you do?Disputing a contractor’s extra-work bill: when is legal help useful?Moving into a newly built home: check the Wkb completion notification firstContractor will not repair defects after completion: what can you do? · NLDisputing a contractor’s extra-work bill: when is legal help useful? · NLContractor stops without finishing your renovation: what can you do? · NLPutting a contractor in default: a notice suited to your building problem · NLFixed price, guide price or time and materials: what building risk are you accepting? · NLHaving a building quotation checked: what does your assignment really include? · NLContractor will not repair defects after completion: what can you do? · PDF (NL)Disputing a contractor’s extra-work bill: when is legal help useful? · PDF (NL)Contractor stops without finishing your renovation: what can you do? · PDF (NL)Putting a contractor in default: a notice suited to your building problem · PDF (NL)Fixed price, guide price or time and materials: what building risk are you accepting? · PDF (NL)Having a building quotation checked: what does your assignment really include? · PDF (NL)Need a lawyer? Agree on the work and costs.Prepare your consultationAll PDF guidesNeed a construction lawyer? Choose help suited to your building disputeFind a lawyerOfficial lawyer registerArticlesArticlesExplainer videosExplainer videosToolsToolsPDF guidesPDF guidesMethod and sourcesMethod and sourcesLegal helpLegal help
Topics

Topics

Understand your position, gather the right documents and explore the next step for your situation.

Contractor will not repair defects after completion: what can you do?Building defects after completion and no repair? Prepare your file and learn when a construction lawyer can assess your next step.
Disputing a contractor’s extra-work bill: when is legal help useful?Unexpected charges for extra building work? Distinguish changed instructions, fixed prices and estimates, and prepare your objection with evidence.
Contractor stops without finishing your renovation: what can you do?Your contractor no longer turns up? Document work and payments and have resumption, a final deadline or replacement assessed legally.
Putting a contractor in default: a notice suited to your building problemA contractor is not keeping agreements? Prepare a specific formal notice identifying the right party, failure, reasonable deadline and evidence.
Fixed price, guide price or time and materials: what building risk are you accepting?Have pricing checked before renovation. Distinguish fixed prices, guide prices, time-and-materials work and provisional sums; record warnings and limits.
Having a building quotation checked: what does your assignment really include?Signing a renovation quotation? Check work boundaries, drawings, exclusions, terms and acceptance before unclear agreements become binding.

Can’t find your question?

Search by question or topic.

Articles